Issue with Timeline capacity calculation

Hi,

I identified a bug where ‘free’ all-day Google Calendar events invisibly deducted 24 hours from Focus capacity.

However, a new issue remains: after removing all calendar connections and simplifying to one task, Focus is still incorrectly multiplying that single task’s time commitment by 2–3x, resulting in a significant over-capacity calculation on the timeline. How can I resolve this capacity overestimation?

So I found a bug that’s causing this.

I’d set a custom daily working schedule in the settings that included a half hour lunch break. So each day had two periods, one before lunch and the other after. Once I set this back to ‘no schedule’ the timeline capacity figures then calculated correctly.