I would like to download a report that shows my actual time spent vs the budgeted time?
Hi Carmel, did you happen to figure this out? I am looking for the same report and having a hard time.
Hey there ![]()
You can see your total hours vs. the estimated hours for a project by:
Going to the Reports section >
Summary report >
Scroll down to the second chart >
Select breakdown by Project and Member >
Click the " + " symbol on the right side and select “Duration” (Actual hours tracked) and “Estimate” (Estimated hours for the project). >
Export the report ![]()
This is available on the Starter plan.
The alternative to see your hours and estimates in a graph (and if you have the Premium plan) is to go to :
Projects >
Select project >
Dashboard >
Here you can see your current hours vs estimated for that project.
Here is a guide regarding the Project Dashboard ![]()